Clearing the Site |
| |
• |
Shrubs/trees/rubble removed |
| |
• |
Pad leveled |
| |
• |
Pad prepared with mesh and plumbing works carried out |
| • |
Putting the Slab Down |
| |
• |
Grano house slab is laid |
| |
• |
This is required to be left to set for a period of 7-10 days to Engineer requirements |
| |
• |
Pest controllers |
| |
• |
Organise termite treatment (Progress Payment Due) |
| |
• |
Window and door frames are delivered and bricks loaded onto site |
| • |
Single storey (Progress Payment Due) |
| |
• |
Ground floor of double storey (Progress Payment Due) |
| |
• |
Formwork is constructed |
| |
• |
Suspended slab poured - required to set for a period of 7-10 days to Engineer requirements |
| |
• |
First floor of double storey (Progress Payment Due) |
| • |
Contact Telstra for Phone Connection |
| • |
The Roof Frame |
| |
• |
Roof carpenter erects roof frame |
| |
• |
Electrician and plumber begin tubing |
| |
• |
Roof cover delivered |
| |
• |
Roof cover laid |
| • |
Render internal walls for preparation of plastering |
| • |
Ceiling flushed and finished (Progress Payment Due) |
| • |
Internal Plastering White Set |
| • |
Inserrt windows and doors, lock-up the house |
| • |
Clean bricks |
| • |
Cupboards |
| • |
Plumbing |
| • |
Ceramic Tiles |
| • |
Painting |
| |
• |
Ceilings, gutters, downpipes |
| |
• |
Internal/external door and door frames |
| |
• |
Fascia, gables (if applicable) |
| • |
Electrical and Plumbing Completed |
| |
• |
Wall oven and hotplate installed |
| • |
Internal Work |
| |
• |
Verticals, carpets, wall painting etc (if applicable) |
| • |
Flyscreens and Driveways if applicable |
| • |
Site Cleaned |
| • |
Practical Completion |
| |
• |
Final inspection with supervisor |
| |
• |
Client to send insurance and letter of approval to bank |
| • |
Collection of Keys |
| |
• |
Upon receival of final paymen, you will need to make an appointment with the Lifestyle
Homes office to collect your keys |